Level 2 · White space · Concept rev D · 12 kW air first

Air-cooled first, liquid next

The existing second floor at 801–809 W 4th St, laid out to fill with 12 kW air-cooled server racks up to the 9.25 MW of power available in Phases I and II, in Halls 1, 2 and 5 on the existing raised floor, and then to add GB300 or Vera Rubin rack-scale systems with in-row liquid cooling in Halls 3 and 4, on the bare slab with their own cooling. Hall 1 stays air-cooled and is built so rear-door cooling can take it to 50 kW a rack in Phase III. The structure is being engineered for very heavy racks, with loads carried down to columns that run to bedrock. Hover any area or numbered marker on the plan to see what it is.

22 MWAnticipated IT, Q2 2028
9.25 MW12 kW air-cooled, Phases I–II,
768 server-rack positions
≈93.5 MWAnticipated IT, Phase IV ~2030
Level 2 white space layout sheet, rev D: 12 kW air-cooled server rows in Halls 1, 2 and 5 on the raised floor, GB300 or Vera Rubin liquid-cooled pods in Halls 3 and 4 on the slab, the network hall, support rooms, legend, capacity table and phase key A B C D E F G H I J K 1 2 3 4 5 6 7 8 9 10 11 1213

GB300 / Vera Rubin rack 12 kW air-cooled rack Air | liquid boundary Future position
Gray existing building · black new · dashed future · earlier layouts: rev B, liquid-first (page) · rev C, air pods

What each part is

Letters mark the rooms and halls; numbers mark the equipment every pod is built from. Room codes in grey are the zone names on the original plan.

Rooms & halls
  • A

    Data Hall 1 · 12 kW air, RDHx-ready

    W2F

    Three bays of four rows: 336 air-cooled server racks at 12 kW on the existing raised floor. The first rows open in Phase I and the rest in Phase II. Hall 1 stays air-cooled; its 5 ft hot aisles leave room for rear-door heat exchangers (RDHx) that can raise racks to about 50 kW in Phase III, on chilled water run under the raised floor.

    336 racks4.0 MW at 12 kW≈17 MW at 50 kW
  • B

    Data Hall 2 · 12 kW air

    W2C

    Two bays of four rows: 224 air-cooled server racks at 12 kW on the existing raised floor, with contained 5 ft hot aisles. Phase I (March 31, 2027) with the network hall, on the existing chilled-water plant.

    224 racks2.7 MW12 kW / rack
  • C

    Network, storage & management hall

    W2E

    80 air-cooled racks (up to 12 kW each) for spine switches, storage and management servers. It sits beside the existing telecom room where carrier fiber arrives. Phase I (March 31, 2027) with Hall 2, before any liquid cooling is in.

    80 racks≈1.0 MW≤12 kW / rack
  • D

    Electrical gallery

    W2H north strip

    One A and one B power distribution switchboard (PDS) per pod, including Hall 3’s (Phase III). Busway leaves here and runs over every row, air and liquid alike. A new wall separates it from Hall 2.

    14 PDS415 V2N A + B
  • E

    Liquid-cooling support

    W2E annex

    Treatment and filtration for the rack coolant loop, expansion tank, glycol make-up, RO water for the humidifiers, a spare CDU and pump cart, and a coolant store with spill kit. It sits on the liquid side, beside Hall 4.

    TCS treatmentRO waterSpares
  • F

    Rack staging, integration & burn-in

    W2M

    Air-cooled server racks and GB300 or Vera Rubin racks (up to 2.2 tons) ship fully built. They are unpacked, proven here on a load bank or test CDU, then roll into a hall. Next to the freight elevators.

    Test CDULoad bank8 ft clear path
  • G

    House & mechanical power

    Existing PDU room

    Panels for lighting, pumps, CRAHs and other building loads, kept separate from IT power. Reuses the existing PDU room between columns 1 and 2.

    MDP panelsBuilding loads
  • H

    Hall 3 · GB300 / Vera Rubin

    W2J

    Two liquid-cooled pods of 32 GB300 or Vera Rubin racks on the bare slab, with in-row CDUs and their own facility-water risers. Phase III adds 10–13 MW here and/or as rear-door upgrades in Hall 1; both pods fill by Phase IV.

    64 racksup to 15.4 MWup to 240 kW / rack
  • I

    Future Hall 4 · GB300 / Vera Rubin

    W2L / G3

    Two future liquid-cooled pods (GB300 or Vera Rubin) on the slab, fed from their own electrical gallery to the south. Phase IV, once the 90 MW expansion is in place.

    64 positionsup to 15.4 MW
  • J

    South electrical gallery

    W2G4

    PDS A and B switchboards for Hall 5 (built in Phase II) and Hall 4 (Phase IV).

    8 PDS415 V
  • K

    Hall 5 · 12 kW air

    W2A / B / Z

    Two bays of four rows: 208 air-cooled server racks at 12 kW, beside Hall 2 so the air halls stay together, with switchboards at the south end. About 130 of them reach 9.25 MW in Phase II; the rest is spare air space. It could convert to liquid pods later.

    208 racks2.5 MW at 12 kW12 kW / rack
Equipment
  • 1

    12 kW air-cooled racks Air · 12 kW

    Standard 600 × 1200 mm racks of air-cooled servers at up to 12 kW each, four rows to a 36 ft bay. Fronts face the cold aisles; backs face contained 5 ft hot aisles.

  • 2

    GB300 / Vera Rubin pod NVL72

    Two rows of 16 racks facing away from one enclosed hot aisle, on the slab in Halls 3 and 4. GB300 draws about 132 kW a rack, Vera Rubin up to 240 kW (600 × 1200 mm overall); both are liquid cooled.

  • 3

    In-row CDUs CDU

    Coolant distribution units. They swap heat between the building water and the clean coolant loop to the racks. About 1,800 kW each, 6 per pod, one more than the load needs (N+1).

  • 4

    Hot-aisle containment HAC · TCS

    The enclosed 5 ft aisle behind each pair of air rows, with doors at both ends, returning hot air to the CRAHs and fan walls. In Hall 1 the width leaves room for rear doors; in the liquid pods it also carries the TCS manifolds.

  • 5

    Facility water header & risers FWS

    Main building water pipes, overhead, feeding the CDUs in Halls 3 and 4 only, so no facility water runs over the air halls. The risers just inside Hall 3 are an assumed location to confirm. Hall 1’s future rear doors would take chilled water under the raised floor instead.

  • 6

    Overhead busway A / B 415 V

    Plug-in power bars above each half-row. A and B come from separate switchboards, so a rack keeps running if one side fails (2N).

  • 7

    Power distribution switchboards PDS-A · PDS-B

    415 V switchboards that feed the busways, one A and one B per pod. At least 4 ft of working space in front of each (NEC 110.26).

  • 8

    Chilled-water CRAH CRAH · CW

    Computer room air handlers and fan walls at the ends of the aisles. They carry all the heat of the 12 kW air halls (9.25 MW by Phase II) and the leftover air heat of the liquid halls. About 200 kW each; the air halls need about 45–50 CRAHs or 25–30 fan walls.

  • 9

    Humidifier H · RO

    Adiabatic ultrasonic humidifier on RO water. Holds 20–80% RH: too dry builds static, too humid risks condensation on cold pipes.

  • 10

    Network racks NET

    Leaf switch rack at each row end, linking every 8-rack scalable unit (SU) to the cluster fabric.

  • 11

    Fiber backbone tray Fiber

    Overhead tray carrying fiber from the NET racks to the network hall and the telecom room.

  • 12

    Air-hall aisles Clearance

    In the air halls each 36 ft bay holds four rows: a 6 ft 3 in cold aisle on each column line, 5 ft contained hot aisles and a 4 ft cold aisle mid-bay. The liquid halls keep 23 ft cold aisles for rolling in 2.2-ton racks. End aisles are 14 ft at the north (gallery) end.

  • 13

    Air | liquid boundary Line 8

    The existing wall on column line 8, with a plenum dam under the raised floor and a 1:12 ramp (18 in) between the raised-floor air halls and the slab-level liquid halls. Halls 2 and 5 could later convert to liquid pods; Hall 1 stays air.

Capacity

Two numbers matter here. Floor capacity is what every drawn rack position would draw if filled, about 41 MW of IT as drawn: ≈10.2 MW of 12 kW air-cooled positions in Halls 1, 2 and 5 and the network hall (the power caps Phases I–II at 9.25 MW), and 30.7 MW of GB300 or Vera Rubin positions in Halls 3 and 4. Anticipated IT capacity is what the power supports: 2.7 MW today. The facility already has 20.5 MW of raw power, but much of it is held back by legacy 2N failover switching and wiring. Rewiring and new UPS systems should free about 9–11 MW of IT with no new utility power. Duke Energy feed increases of 2.5 MW and 14 MW then bring the facility to just above 37 MW of raw power and 22 MW of IT by Phase III. There is no plan to go further until Phase IV, an additional 90 MW of raw power from Duke Energy expected around 2030. Like the earlier increases, it connects through new infrastructure rather than the legacy switching. It is planned at a PUE of 1.2–1.3, adding about 69–75 MW of IT, roughly 88–93.5 MW in all. The liquid halls are on busway sized for 240 kW Vera Rubin racks; Hall 1’s busway is sized for 50 kW racks, so its rear-door upgrade needs no new power distribution.

Floor IT capacity · every drawn position filled (Level 2)
AreaSystemRacksFloor IT capacity
Hall 2 · W2C · Phase I12 kW air-cooled servers2242.7 MW
Network hall · W2E · Phase IAir-cooled IT80≈1.0 MW
Hall 1 · W2F · Phases I–II12 kW air, RDHx-ready3364.0 MW
Hall 5 · W2A/B/Z · Phase II12 kW air-cooled servers2082.5 MW
Air halls + network9.25 MW used by Phase II768 + 80≈10.2 MW
Hall 3 · W2J · Phase III onGB300 / Vera Rubin64up to 15.4 MW
Hall 4 · W2L/G3 · Phase IV, ~2030GB300 / Vera Rubin64up to 15.4 MW
Floor capacity as drawn768 + 128 + 80≈40.9 MW
Hall 1 on rear doors at 50 kW (Phase III on)RDHx336≈16.8 MW
Halls 2 and 5 converted to liquid podsGB300 / Vera Rubin128up to 30.7 MW
Anticipated IT capacity · what the power supports (facility)
PhaseReady for serviceRaw powerIT capacity
TodayNow2.7 MW
Phase IMar 31, 20274.05 MW
Phase IISep 30, 20279.25 MW
Phase IIIApr 30, 202837+ MW22 MW
Phase IV · 90 MW expansion (Duke Energy)~2030+90 MW → ≈127 MW+75 MW → ≈93.5 MW

The new Duke Energy feeds (2.5, 14 and 90 MW, 106.5 MW in all) connect through new infrastructure, not the legacy 2N switching, so they are planned at a PUE of 1.2–1.3. Phase IV’s 90 MW is shown at 1.2 (90 ÷ 1.2 = 75 MW IT). At 1.3 it would be about 69 MW. After it, the anticipated ≈93.5 MW of IT is more than Level 2 can hold even fully upgraded (≈79 MW: Hall 1 on rear doors at 50 kW, Halls 2–5 as liquid pods), so Level 2 can be fully built out, with power left for the rest of the facility. Phases I and II allow only 12 kW air-cooled racks: Phase I uses all 4.05 MW on the network hall, Hall 2 and the first rows of Hall 1, and Phase II reaches 9.25 MW with the rest of Hall 1 and part of Hall 5, on the existing chilled-water plant. Phase III adds 10–13 MW, capped at the 22 MW the power supports: GB300 or Vera Rubin in Hall 3, and/or rear-door upgrades that take Hall 1 toward 50 kW a rack. Hall 4 follows in Phase IV.

Air-cooled server racks: up to 12 kW and about 1 ton each (CPU, storage or lighter GPU servers); Hall 1’s rear doors would take them to about 50 kW. GB300: about 132 kW a rack. Vera Rubin: up to 240 kW, four 110 kW power shelves, 600 × 1200 × 2300 mm overall (GIGABYTE, Aivres; the MGX body is 1,068 mm deep plus a 132 mm rear extension), ~1,800 kW in-row CDU (GIGABYTE). Footprints, weights (≈2.2 tons Vera Rubin, a planning weight with margin, since NVIDIA gives about 4,000 lb) and floor loads (row-area averages ≈134 psf air, ≈297 psf liquid pods, ≈500 psf peak) are estimates. Future halls are anticipated to come online in Phase IV, once the 90 MW expansion is in place. Phase IV is an additional 90 MW of raw utility power under the pending Duke Energy application, expected around 2030, bringing the facility from just above 37 MW at Phase III to about 127 MW.

Power

2N. The UPS is on P1, three floors down. Medium-voltage switchgear, generators and other support equipment are on P1, P2 and in the Annex. UPS feeders rise to the A and B switchboards for each pod in the north gallery (D), and those feed 415 V busway over every half-row.

Cooling

Air halls: chilled-water CRAHs and fan walls with contained hot aisles; at 12 kW a rack, perforated tiles on the 18 in floor can carry part of the supply. Hall 1’s rear doors later run on chilled water under the floor. Liquid halls: facility water to in-row CDUs, a clean TCS loop to the cold plates, and CRAHs for the residual air.

Environment

20–80% RH non-condensing, with loop supply kept above room dew point. Leak detection under every pod, plus VESDA. The halls are protected by a pre-action sprinkler system, so the pipes over the racks stay dry until the fire detection system releases water into them. The new containment, overhead wiring, cooling and networking are all built to fire code.

To confirm

The post-tension tendon layout and tendon-free zones for openings, beam depths within the 14 ft slab to slab, elevator door height and sill level against the raised floor, the added slab support design, riser space for UPS feeders from P1, facility water risers and heat rejection, final Vera Rubin specs from NVIDIA, CRAH and fan-wall capacity for 9.25 MW of air, chilled water for Hall 1’s rear doors, and the plenum dam and ramp at the boundary.

Phasing

12 kW air first, liquid next

Phases I and II allow only 12 kW air-cooled racks, so the plan above fills Halls 2, 1 and 5 with dense air-cooled rows on the existing raised floor until the 9.25 MW of Phase II power is used. Halls 3 and 4, on the east side next to the liquid-cooling support room, are kept for GB300 or Vera Rubin pods with their own cooling on the bare slab. Hall 1 stays air-cooled and can step up to about 50 kW a rack with rear-door heat exchangers in Phase III.

Air-cooled, 12 kW racksRear doors, up to 50 kWLiquid-cooled GB300 / Vera RubinLiquid, partly filledCould convert to liquid podsNot yet in service
Rev D · 12 kW air first, as drawn
HallFloorPhase IPhase IIPhase IIIPhase IV
Network hall18 in floor keptAir · 1.0Air · 1.0Air · 1.0Air · 1.0
Hall 218 in floor keptAir · 2.7Air · 2.7Air · 2.7→ liquid pods possible
Hall 118 in floor kept, rear-door readyAir · 0.4Air · 4.0Rear doors · toward 50 kWRear doors · ≈16.8
Hall 518 in floor kept—Air · 1.6Air · 1.6–2.5→ liquid pods possible
Hall 3No raised floor, on the slab——GB300/VR · partGB300/VR · 15.4
Hall 4No raised floor, on the slab———GB300/VR · 15.4
Level 2 IT in use, MW4.059.2519.3–22up to ≈79

MW are nominal IT. Phase I: the network hall (≈1.0 MW), all 224 racks of Hall 2 (2.7 MW) and about 33 racks of Hall 1, using all 4.05 MW. Phase II: the rest of Hall 1 (336 racks, 4.0 MW) and about 130 racks of Hall 5, reaching 9.25 MW; about 78 air positions stay spare. Phase III adds 10–13 MW, capped at 22 MW, as GB300 or Vera Rubin in Hall 3 (7.7 MW a Vera Rubin pod) and/or rear-door upgrades in Hall 1. Phase IV: Hall 4, Hall 1 fully on rear doors, and Halls 2 and 5 can convert. Like the capacity table, this assumes each phase’s IT capacity is available to Level 2.

Air halls (1, 2, 5)

Four rows of 600 × 1200 mm racks in each 36 ft bay: a 6 ft 3 in cold aisle on each column line, 5 ft contained hot aisles and a 4 ft cold aisle mid-bay, with 60 ft rows (56 ft in Hall 5). The existing 18 in raised floor stays for cabling and some tile supply. 12 kW racks weigh about 1 ton, so these halls need no new steel.

Hall 1 rear doors

Hall 1 stays air-cooled. Rear-door heat exchangers on chilled water, piped under the raised floor, can take its racks toward 50 kW in Phase III (about 16.8 MW for all 336). Its 5 ft hot aisles stay about 3 ft 8 in wide with doors fitted, and its busway is sized for 50 kW racks.

Liquid halls (3, 4)

GB300 or Vera Rubin pods of 32 racks on the bare slab with no raised floor, in-row CDUs, a TCS loop and their own facility-water risers just inside Hall 3, next to the liquid-cooling support room. The new beams under the rows go in only here.

The boundary

The existing wall on column line 8, with a plenum dam under the raised floor so the air halls’ plenum stays sealed, and a 1:12 ramp (18 in) with a door so people and racks move between the raised floor and the slab.

Checks
Chilled-water plant

Phases I–II put 9.25 MW of 12 kW air-cooled IT on the existing plant, about 10.4 MW with fans and lighting. The ten existing roof chillers (3,570 tons, ≈12.6 MW) can carry it, but with little margin: about 11.3 MW with one chiller out. Phase I’s 4.05 MW alone is comfortable. Confirm the plant’s real capacity and what else it serves.

Airflow

About 125 cfm per kW at a 25 °F rise, so 4.05 MW needs ≈510,000 cfm (about 12–14 fan walls of 350–400 kW, with spares) and 9.25 MW needs ≈1.17 million cfm (about 27–30), far more than the CRAHs drawn today. They have to fit along the cold-aisle ends; this is the main space check for the air zone.

Power

Unchanged switchboards. 12 kW air racks use a small part of a busway tap; Hall 1’s busway is sized for 50 kW racks for the rear-door upgrade, and the liquid halls’ for 240 kW.

Hardware

12 kW suits CPU, storage and lighter air-cooled GPU servers. Rack-scale GB300 and Vera Rubin NVL72 are liquid-only, so they go in Halls 3 and 4.

Earlier layouts. Rev B, liquid-first: page · sheet · layout PDF · floor loads PDF. Rev C, ≈30 kW air pods west, Vera Rubin east: sheet. First air-first draft: sheet.

Structure

Built for very heavy racks

Liquid-cooled rack-scale systems weigh far more than conventional IT, and the next generations will be heavier still. Level 2 is being engineered for them. Rack loads come off the slab onto steel and go down columns that run to bedrock.

2.0–2.2 tonsper rack, shipped fully built
≈560 psfunder a 2.2-ton rack’s 600 × 1200 mm footprint
≈1,100 lbon each caster while a 2.2-ton rack rolls
Bedrockwhere the columns land, with capacity to spare

How the steel works together: each rack row sits on its own beam, the beams run continuously across the girders on column lines C, D and E, and the girders frame into the existing columns. The slab and racks are drawn lifted so the steel can be seen; in the building they sit directly on the beams.

confirmed
Post-tensioned slabs

The WEC floors are post-tensioned: steel tendons under high tension carry the slab, so cutting one is dangerous and costly to repair. Every new anchor, core or pipe opening is placed only after the tendons are mapped, and the new steel takes its load at the columns and existing beams instead of being drilled through the slab.

in place
Carbon fiber on the slab

The Level 2 slab has already been strengthened with carbon fiber, raising its original load capacity.

anticipated
New steel under the slab

A steel beam in the Level 1 ceiling directly under each rack row, carried by girders on the column lines that frame into the columns, so the rows no longer depend on the slab span. See the steel layout on the floor-load map.

anticipated
Steel base frames under every row

Racks and CDUs sit on steel frames that spread their weight and carry it toward the column lines. This applies to every floor option, A through E. Frames and steel are sized with margin above today’s 2.2-ton racks, so heavier future NVIDIA generations fit the same positions.

confirmed
Columns down to bedrock

Engineers have confirmed the columns are large, run down to bedrock and can carry far more than the building will ever hold. They anchor the whole load path.

anticipated
A protected roll-in route

Steel plates or heavy-duty panels run from the freight elevators to each row, rated for a 2.2-ton rack rolling on casters.

Next engineering steps: scan the slab (ground-penetrating radar or X-ray) to map the post-tension tendons, the carbon-fiber strips and the rebar, check tendon condition and anchorages, confirm the strengthened slab’s rated capacity, mark tendon-free zones for anchors and pipe openings, and set a design load for each rack position with margin for future racks: at least 5,000 lb (2.5 tons) per rack is suggested, since Kyber-generation racks (2027+) have no published weight yet and will be heavier. Then size the new steel and base frames. All of it is designed and stamped by the structural engineer of record. Commissioning equipment fits within the same design: liquid-cooled load banks for testing weigh up to about 1.1 tons, roughly half a rack. See the estimated floor load map (PDF).

Commissioning

Proven before handover

Every hall is tested under simulated load before any tenant equipment goes in. Testing follows the five standard commissioning levels, from factory checks to a full integrated systems test of each hall.

LevelStageWhat is proven
L1Factory acceptanceMajor equipment (UPS, switchgear, generators, CDUs, chillers) is tested at the manufacturer before it ships.
L2Site acceptanceEach item is checked on arrival and after installation: right equipment, installed correctly, ready for power.
L3Pre-functionalEach system is started on its own. UPS, batteries, generators and switchgear are run under test load.
L4FunctionalEach system is run under controlled load across its full range, including the liquid-cooling loops.
L5Integrated systems testThe whole hall is run end to end under simulated IT load, with power and cooling together, including failures and switchover.
Power and cooling tested together

AI loads can jump in seconds. As they do, pumps, CDUs and chillers ramp up and draw more power themselves. Testing power and cooling separately can miss problems that only appear when they interact, so each hall’s final test runs both at once.

Liquid halls tested through the coolant

The liquid halls (Halls 3 and 4) are tested with load banks that heat the coolant loop, proving pump performance, flow, temperature rise across the loop and heat rejection. Air-heating load banks test the 12 kW air halls (Halls 1, 2 and 5) and the network hall at full air load.

Each phase proven before it goes live

Testing follows the build-out. Every phase is commissioned to L5 before tenants use it, and is isolated so that testing a new phase never disturbs halls already in service.

Results documented for tenants

Test data are logged throughout. Tenants can receive the reports as evidence of the capacity and redundancy they are leasing.

Commissioning is carried out by an independent commissioning agent using load banks sized to each hall. Specific equipment and suppliers are chosen when each phase is scoped.

Structure

Floor loads

Estimated equipment weight across Level 2 at full build-out (Phases I–IV), averaged over 4 × 4 ft cells, with the concept steel that carries the rack rows drawn over it. The GB300 / Vera Rubin rows in Halls 3–4 are the heaviest, at about 500 psf; the 12 kW air halls average about 134 psf over their rows. Hover any cell to read its load, or any beam or girder for its spans.

0–100 psf100–200 psf200–300 psf300–400 psf400–500 psf≥ 500 psfBeam under a rack rowGirder on a column lineColumnFuture halls

Averages over the row area: 12 kW air bays about 134 psf, liquid pods about 297 psf. Rack weights come from this page (Vera Rubin 2.2 tons, air-cooled server racks about 1 ton); CDUs, switchboards and other equipment use planning estimates, not vendor data. Equipment weight only: no floor system, slab self-weight or code live load. The structural engineer of record sets design loads. Full sheet with every assumption and the steel layout (PDF).

Equipment weights and footprints · planning estimates used for the map. Bars on the left are weight per item; bars on the right are that weight spread over the item’s own footprint, coloured on the map’s scale.
ItemFootprintWeight, lb eachpsf on its footprint
GB300 / Vera Rubin NVL72 rack600 × 1200 mm overall; 5,000 lb design allowance recommended2.0 × 3.9 ft7.9 sq ft
4,400 · 5,000 design
558
Air-cooled server rack, 12 kW600 × 1200 mm; Halls 1, 2, 5 (Hall 1 rear doors to 50 kW)2.0 × 3.9 ft7.9 sq ft
2,000
254
In-row CDU, filled≈1.8 MW; liquid pods only, three per row over the D girder4 × 4 ft16.0 sq ft
6,000
375
PDS switchboard line-up415 V busway switchboard, electrical gallery14 × 4 ft56.0 sq ft
9,000
161
CRAH / fan-wallchilled water8 × 3 ft24.0 sq ft
3,000
125
Network (NET) rackone at each end of every row2 × 4 ft8.0 sq ft
2,000
250
Air-cooled IT racknetwork hall2 × 4 ft8.0 sq ft
2,000
250
Support / staging equipment12 × 5 ft60.0 sq ft
3,000
50
Humidifier2 × 3 ft6.0 sq ft
500
83

Dashed gold end on the GB300 / Vera Rubin bar: the 5,000 lb design allowance (≈635 psf on its footprint). Not in the map: hung loads (facility-water headers in the Level 1 ceiling, TCS manifolds, containment), MEP allowances and code live load.

Same racks, different psf · the answer depends on the area the weight is averaged over.
Averaged overpsf
On one rack’s own footprint4,400 lb ÷ 7.9 sq ft
558
Peak 4 × 4 ft map celldarkest cells in the Vera Rubin rows
497
Liquid pod average over the rowsracks, CDUs, NET racks and hot aisle
297
62,000 lb pod over a 320 sq ft containerspread over its whole base, aisles included
194
12 kW air bay average, for comparison4 rows of 28 racks per bay, aisles included
134

Steel under the rows (concept). Every liquid-cooled rack row sits directly on its own north–south beam in the Level 1 ceiling, so the slab only passes the load straight down and never has to span it. The beams run continuously over the lettered column lines and are carried there by east–west girders framed into the existing columns: in Hall 3 over lines C, D and E (36 ft + 24 ft spans) and in Hall 4 over F, G and H, with each row ending on the E girder and each pod’s CDU cluster centred over the D girder. The rows stay where they are: centring pods on the column lines would put columns in the hot aisles and cost a pod in each hall, because the hall walls sit on column lines. Concept quantities: 8 row beams (4 by Phase III, 4 in Hall 4), 12 girder runs, about 35 tons of new steel (≈18 tons by Phase III), sized roughly as W24 beams and W27–W30 girders at a 5,000 lb rack allowance. Rack positions are fixed before the steel is fabricated, and base frames get slotted adjustment so later racks still land on the beams. The 12 kW air halls and the network hall stay on the slab; Halls 2 and 5 would get beams only if they convert to liquid pods. The structural engineer of record sizes and stamps all of it. Hover any beam, girder or column for details.

Layout aligned to the steel · what was weighed

  • The change. The pods in Halls 1 and 2 and Future Hall 3 moved 4 ft 10 in north. Each row now ends exactly on column line E, and each pod’s CDU cluster sits centred over the D girder.
  • No cantilever. Before, the last ≈5 ft of every row hung past the E girder. Racks on a cantilever deflect more at the tip, and the rack liquid manifolds and quick-disconnects do not tolerate racks moving against each other.
  • Heaviest loads on the girder. The three in-row CDUs per row (≈6,000 lb each, filled) are the largest point loads on the floor. Centred on D they go almost straight into the girder and the columns.
  • Lighter beams. Without the cantilever and with the CDUs at a support, the row beams can likely drop about one size; the steel total falls slightly (≈35 tons in rev D, where only Halls 3–4 get beams).
  • Unchanged. Pod count and racks, the 36 ft pod pitch, 24 ft cold aisles, 5 ft hot aisles, 12 ft row pairs and 48 ft rows. Busway drops from the electrical gallery are 4 ft 10 in shorter; the facility-water headers and riser moved north with the CDUs; fiber drops to the backbone tray are longer.
  • End aisles. North end aisle (to the CRAHs at the gallery wall) 18 ft 10 in → 14 ft, still ample for rolling 600 × 1200 mm racks and CDUs in on pallet jacks and for CRAH service; south end aisle 18 ft 10 in → 23 ft 8 in.
  • Considered and rejected. Centring pods on the column lines (columns would sit in the 5 ft hot aisles, and each hall would lose a pod because the hall walls sit on column lines); turning rows east–west (racks would bridge between beams and the slab would bend again); sliding pods sideways toward the columns (little gain once beams carry the rows).
  • Left as is. Future Halls 4 and 5 (lines F–H): their rows already sit inside the spans. Future Hall 4’s rows start ≈3 ft north of the F girder: the beams stop at the girder (they are not extended past it), and the NET racks at that end sit on the base frame bearing on the girder. The pods can move 3 ft south when that hall is designed.
  • Still to confirm. Column positions against the as-built drawings (including the 5/6 joint), egress widths in the end aisles, busway drop routing, and every member size: the structural engineer of record designs and stamps the steel.

Working within 14 ft

Level 2 is 14 ft slab to slab, and racks are about 88 in tall. Today an 18 in raised floor carries the wiring and air cooling, and all of it can be redone. Below are five ways to use the height, from keeping the floor to removing it entirely. Water and power are kept apart in each, and services sit side by side instead of stacked.

Option A

Keep the 18 in floor

Keep the existing 18 in raised floor as a wet plenum. Coolant runs below, power and fiber above, and facility water over the cold aisles only.

Height budget
ZoneAllowTop at
Raised floor (wet plenum)18 in1 ft 6 in
Rack, air-cooled or Vera Rubin88 in8 ft 10 in
Hot-aisle containment roof4 in9 ft 2 in
Clear to sprinkler deflectors18 in10 ft 8 in
Sprinkler branch lines8 in11 ft 4 in
Left for slab above + beams≈32 in14 ft 0 in
How it works
Keep it, but stop using it for air

Today the floor carries the wiring and the air cooling. In the new layout it carries no air: every perforated tile is closed. The CRAHs (8) blow straight into the cold aisles and the hot-aisle containment returns. In rev D this is the floor of the 12 kW air halls (1, 2 and 5): at 12 kW a rack, perforated tiles in the cold aisles can carry part of the supply, with CRAHs and fan walls doing the rest.

Make it the wet zone

Coolant (TCS) pipes run under the floor from each CDU and rise into the hot-aisle manifolds. Every joint sits over a drip pan, leak-detection rope runs the full floor, and each pod gets a drain point. Water stays under the racks and power stays over them.

Carry the racks on steel, take the load to the columns

A 2.0–2.2-ton rack on four casters puts about 1,000–1,100 lb on each wheel. That is more than most access-floor panels are rated to roll. The slab has already been strengthened with carbon fiber, but the rack rows will likely need more support. Engineers have confirmed the columns are large, run down to bedrock and can carry far more than the building will ever hold. So rows and CDUs sit on steel frames that carry their weight toward the column lines, with new steel under the slab if needed, instead of relying on the slab alone. Because the slabs are post-tensioned, that steel bears on the columns and existing beams, frames use as few slab anchors as possible, and every anchor or pipe opening goes in a scanned, tendon-free spot. Heavy-duty panels go along the roll-in path. The structural engineer sizes the steel.

Strip it first

All of today’s underfloor wiring and cooling can be redone, so it comes out before anything new goes in: cable, power whips and any piping. Then the plenum is cleaned, sealed and re-levelled. Power and network cabling return overhead.

Access is already in place

Access from the freight elevators to the raised floor is already handled within the facility.

Option B

Raise the floor to 30 in

Replace the floor with a 30 in floor so every water pipe, facility headers included, runs below the racks. Overhead carries only busway, fiber and sprinklers.

Height budget
ZoneAllowTop at
Raised floor (all water)30 in2 ft 6 in
Rack, air-cooled or Vera Rubin88 in9 ft 10 in
Hot-aisle containment roof4 in10 ft 2 in
Clear to sprinkler deflectors18 in11 ft 8 in
Sprinkler branch lines8 in12 ft 4 in
Left for slab above + beams≈20 in14 ft 0 in
How it works
Everything wet goes below

Facility water headers run under the cold aisles and coolant (TCS) branches under the hot aisles, so there is no water overhead at all. Drip pans sit under every joint, leak-detection rope runs the full floor, and each pod gets a drain.

A new floor throughout

30 in is a new floor system, because the existing 18 in grid can’t simply be raised. Rows and CDUs still sit on steel frames that carry their weight toward the column lines.

It costs a foot of headroom

Only about 20 in is left for the slab above and its beams. That works only where beams are shallow or run along the hot aisles, so the beam survey decides it.

Elevator access needs rework

The facility’s existing access from the freight elevators is built for the 18 in floor. A floor 12 in higher means that access has to be reworked.

Option C

No raised floor, services hung overhead

Remove the raised floor. Racks sit on the slab at elevator level, and every service, water included, hangs from the slab above.

Height budget
ZoneAllowTop at
No raised floor, racks on slab0 in0 ft 0 in
Rack, air-cooled or Vera Rubin88 in7 ft 4 in
Hot-aisle containment roof4 in7 ft 8 in
Clear to sprinkler deflectors18 in9 ft 2 in
Sprinkler branch lines8 in9 ft 10 in
Left for slab above + beams≈50 in14 ft 0 in
How it works
Racks on the slab

Rows sit directly on the carbon-fiber-strengthened slab, on steel base frames that carry their weight toward the column lines. New steel goes under the slab from Level 1 wherever the structural engineer needs it.

All services overhead

Facility water runs over the cold aisles, and coolant manifolds run over the hot-aisle containment, dropping to each rack. Busway goes over the racks and fiber at the rack fronts. Every water line sits over a drip tray with leak detection, and none runs directly above busway.

The most headroom

About 50 in is left for the slab above and its beams, so this works even if the beams turn out to be deep.

Level with the elevators

Racks roll straight from the two 6,000 lb freight elevators into the halls, with no ramp or lift. It is the fastest way to move 2.0–2.2-ton racks.

The trade-off

Water runs above the racks, and leak protection relies on drip trays instead of a floor plenum. The overhead space is the busiest of the three options to coordinate.

Anchor between the carbon fiber

Everything here hangs from the slab above, which has carbon-fiber strengthening. Hanger anchors have to land between the carbon-fiber strips and never cut through them, so the strips get mapped before any layout is fixed.

Option D

No raised floor, free-standing service frame

Remove the raised floor and carry every overhead service on a steel frame that stands on the floor, so nothing is anchored into the strengthened slab above.

Height budget
ZoneAllowTop at
No raised floor, racks on slab0 in0 ft 0 in
Rack, air-cooled or Vera Rubin88 in7 ft 4 in
Hot-aisle containment roof4 in7 ft 8 in
Clear to sprinkler deflectors18 in9 ft 2 in
Sprinkler branch lines8 in9 ft 10 in
Left for slab above + beams≈50 in14 ft 0 in
How it works
Nothing hangs from the slab above

A steel frame stands on the floor at each row pair, with posts just outside the rack fronts and a beam over the row. It carries the busway, fiber trays, coolant manifolds and containment roof. Nothing is anchored into the carbon-fiber-strengthened slab above.

Load goes down, not up

The frame posts sit on the same steel base frames as the racks, which carry the load toward the column lines. Engineers have confirmed the columns have capacity to spare.

Faster, cleaner fit-out

Frames can be prefabricated and set row by row, with services pre-hung, so most of the overhead work happens at floor level. Each pod can be built out in step with its phase.

Still racks on the slab

There is no raised floor, so racks roll straight in from the freight elevators. Water is overhead on the frame, over drip trays, as in option C.

The trade-off

The frame posts take some aisle width at the rack fronts, and the frame itself is extra steel to buy and coordinate.

Option E

No raised floor, hot-aisle pipe chase

Remove the raised floor, run coolant in a shallow grated chase down each hot aisle, and bring facility water up from the Level 1 ceiling. Nothing wet runs overhead.

Height budget
ZoneAllowTop at
Racks on slab (10 in chase in hot aisle only)0 in0 ft 0 in
Rack, air-cooled or Vera Rubin88 in7 ft 4 in
Hot-aisle containment roof4 in7 ft 8 in
Clear to sprinkler deflectors18 in9 ft 2 in
Sprinkler branch lines8 in9 ft 10 in
Left for slab above + beams≈50 in14 ft 0 in
How it works
A pipe chase only where the pipes are

Instead of a whole raised floor, a shallow 10 in grated chase runs down each hot aisle. Coolant (TCS) pipes run inside it and connect to the back of each rack. The cold aisles, where racks are rolled in, stay at slab level.

Facility water from below

Facility water headers run in the Level 1 ceiling and rise through a slab core at each CDU. Nothing wet is overhead on Level 2, and there is no raised floor.

Most headroom, driest overhead

Overhead carries only busway, fiber and sprinklers, which leaves about 50 in for the slab above and its beams.

Leaks stay contained

The chase is a lined, sloped pan with leak-detection rope and a drain. Pipes in the Level 1 ceiling run over drip pans so a leak never reaches the floor below.

The trade-off

Each CDU needs a core through the carbon-fiber-strengthened slab, placed between the strips and approved by the structural engineer. It also needs room in the Level 1 ceiling for the headers.

Side by side

All five options use the same racks, pods and phasing. They differ only in where the water runs, what hangs from the strengthened slab above, and how much height is left over.

A · Keep the 18 in floorB · Raise the floor to 30 inC · No raised floor, services hung overheadD · No raised floor, free-standing service frameE · No raised floor, hot-aisle pipe chase
Left for slab above + beams≈32 in≈20 in≈50 in≈50 in≈50 in
Water above the racksFacility water, over the cold aislesNoneFacility water + coolant manifoldsFacility water + coolant manifolds, on the frameNone
Leak containmentFloor plenumFloor plenumDrip trays overheadDrip trays overheadChase pan + drip pans in the Level 1 ceiling
Anchors into the slab aboveBusway, trays, waterBusway, traysEverythingNoneBusway, trays
Access from the elevatorsAlready handled in the facilityExisting access reworked for +12 inLevel with the elevatorsLevel with the elevatorsLevel with the elevators
Floor workStrip, reseal, steel under the rowsAll-new floor, steel under the rowsRemove the floor, steel base framesRemove the floor, set service framesRemove the floor, build chases, core the slab
Best ifBeams leave ≈32 in or moreBeams are shallow (≈20 in)Any beam depthThe slab above should not take anchorsLevel 1 ceiling has room and slab cores are approved

The beam survey and the carbon-fiber layout decide it. These are planning allowances, not survey dimensions. 14 ft is taken as top of slab to top of slab, with about 8 in for the slab above.

Abbreviations on the drawing

Every short form used on the plan and in this guide.

2N
Two complete, independent power paths, each able to carry the full load
A / B
The two independent power sides feeding every rack
CDU
Coolant distribution unit: heat exchanger and pumps between FWS and TCS
CRAH
Computer room air handler, cooled by chilled water
CW
Chilled water from the central plant
est.
Estimated planning value to confirm with NVIDIA, the OEM or the engineer
FWS
Facility water system, the building cooling loop that feeds the CDUs
GB300
NVIDIA Grace Blackwell Ultra superchip generation
H
Humidifier
HAC
Hot-aisle containment
IT
Power used by the computers themselves
MDP
Main distribution panel for house and mechanical loads
MEP
Mechanical, electrical and plumbing engineering
MGX / Oberon
NVIDIA rack standard used by GB300 and Vera Rubin; Vera Rubin builds add a rear extension to 1,200 mm deep
N+1 / N+2
One or two more units than the load needs
NEC 110.26
Code section that sets working space in front of electrical gear
NET
In-row network (leaf switch) rack
NVL72 / NVL144
GPUs linked by NVLink in one rack. NVIDIA first called the Vera Rubin rack NVL144 (counting GPU dies) and renamed it NVL72 (counting GPU packages); NVL144 now means the larger Kyber rack
PDS
Power distribution switchboard feeding one pod’s busway
PDU
Original plan’s name for the power room in columns 1–2
psf
Pounds per square foot of floor load
RDHx
Rear-door heat exchanger: a water-cooled coil in a rack’s back door
RH
Relative humidity
RO
Reverse osmosis purified water
SU
Scalable unit of 8 NVL72 racks; a pod holds 4
TCS
Technology cooling system, the clean loop to the rack cold plates
UPS
Uninterruptible power supply, assumed off this floor
VESDA
Very early smoke detection apparatus
VR
Vera Rubin
W2…
Original 2nd-floor zone names, kept for reference
Sources

Vendor and press sources for the equipment sizes, weights and ratings on this page. Weights for switchboards, network racks, humidifiers and support equipment are planning estimates where no published figure was found.

Racks

Cooling

Power and switchboards